Greymont phase 2 goes LIVE!

VUMA is happy to announce that after many hours of trenching, hauling and splicing fibre, phase 2 of Greymont is now LIVE! The next phases will follow shortly, so stay tuned and get ready to experience the exciting world of high-speed broadband. Over the course of the project, we have trenched passed over 900 homes to get
+ Read More

Greymont Fibre Construction Update

Good day Greymont residents, We are in the first month of our build and already a few days ahead of schedule, we like our trenching to be as fast as our high-speed fibre network. The trenching phase that you see in the picture, Second Street, consists of us digging up sidewalks and laying down protective
+ Read More

Fibre Rollout plan for Greymont

Hi you awesome Greymonters The Vuma build rollout plan has been released! You can view it here: https://goo.gl/kucJse Screenshot below: This is the process:

Fibre construction will begin this week.

Good day Greymont residents, VUMA is excited to announce that construction will begin this week. For your convenience have a look at the Greymont rollout schedule to get a better understanding of which phase you fall into and when you can expect construction to take place outside your property. VUMA representatives will be engaging with
+ Read More

VUMA Is Coming to Greymont!

Message from the Vuma Team to those residents interested in Fibre Good Day, I trust this mail finds you well. I have your details from our moral commitment list for the Greymont fibre project where you took in an interest in our planned fibre roll-out to your suburb. During our build we place a small
+ Read More

VUMA is bringing Fibre to Greymont – work starts in Febuary

Good day Greymont residents, Vumatel has officially opened our doors for 2017 and would like to wish all of the residents in Greymont a very happy new year. Construction Start Dates VUMA plans to begin construction in Greymont within the first two weeks of February. The initial phase of the construction process will include scanning
+ Read More

Apologies Greymont – Vumatel

Good day Greymont residents, We apologise for the miscommunication. VUMA has made the call to delay the start of construction in the area, as we feel that we will not have enough time to civilly complete the project before the festive season. The JRA implement a month long shut down over the December period. Johannesburg
+ Read More

Vumatel Feedback on Fibre in Greymont, its great news!

We might have Fibre before Christmas!!! Our awesome chairman Shane had a great meeting with Vumatel and has been kind enough to give us the answers to the main questions we all wanted to know. What is the planned start of the installation date and expected date of completion? Installation will start at the end